Report Description: this report displays contractors who are late on reporting certified payroll, based on the parameters you choose. It shows the following information:
- Project name
- Contractor name
- Contractor contact name
- Contractor address, phone number and email address
- Contractor assignment (who the contractor works for, either the Prime or another contractor)
- Week end date of CPR
- Due date
- Days late
- Status of CPR
NOTE: If the contractor’s week end date has changed, and the new week end date is more than a three-day difference, the report will no longer be accurate because it will still be working off of the original week end date.
Please ensure the Non-Construction Contractor box is NOT checked to ensure your contractor shows on this report.